Tuesday, December 10, 2019

Project Management Principles and Strategies

Question: Discuss about the Project Management for Principles and Strategies. Answer: Introduction The Narrabri Airport Master Plan was adopted in 2012-13. In this plan, proposal was passed to completely revamp the whole Narrabri Airport with latest technology and make it fully functional on a permanent basis. The plan also included expansion of the airport in order to accommodate high capacity aircrafts and introduction of new specific area for jet aircrafts (Projects 2016). The overall master plan was divided into several periods and the project was expected to complete in 2030. In this report, the first phase of the master plan project has been discussed. During this phase, a line marking plan was made for the existing parking apron to accommodate a single larger aircraft such as BAe-146, Dash 8 400 or ATR72 or two smaller aircraft such as B350 King Air or Saab 340 (Ryerson and Woodburn 2016). This was in preparation for Virgin Australia ATR72 operations. It was announced on 18 March 2014 that Narrabri Shire Council had been granted $5.9 million under Round 2 of NSW Resources for Regions program towards the cost of the airside aspects of the runway end of safety areas upgrade project (Tonkin 2014). Works were completed in August 2015. Before initiating the initial phase of the project, the following objectives were set: Rehabilitation of runway 18/36 to accommodate unrestricted operations up to and including Fokker F100 or equivalent. Strengthen and widen existing taxiway to align with final design aircraft requirements and current standards. Rehabilitation and expansion of the existing apron to accommodate final design aircraft requirements and current standards (Bejarano et al. 2015). Apron was expected to accommodate 3 x Fokker F100 and 1 Beech 350 (or equivalent) simultaneously. There would be a 240 metre runway extension of 18/36 to the south as part of the rehabilitation of the existing runway. Provision of new General Aviation area providing parking and aircraft access to the new fuel facility and RFS station. Associated pavement markings on all new aircraft movement areas. All new airfield ground lighting including runway, taxiways and apron. Installation of new single sided Precision Approach Path Indicators (PAPI) to assist aircraft on approach and to comply with standards for Jet Regular Public Transport (RPT) operations. Removal of existing aviation fuel facilities and installation of new facility within the general aviation area. The new fuel facility would provide for self service Jet A1 and Avgas bowsers as well as a Jet A1 tanker for pressure and over wing refueling of larger Jet and Turboprop aircraft (Bejarano et al. 2015). Project Stakeholder Analysis In the first phase of the project, a number of stakeholders were involved, who had their own duties in conducting the project successfully (Chevalier 2016). A stakeholder analysis table is given below. Stakeholder (Team or Individual) Role Responsibilities Issues raised by this stakeholder What are the stakeholder's expectations? What is the level of influence of this stakeholder? How much does this stakeholder support the project? How will we engage this stakeholder? Narrabri Shire Council Chairman External Sanction of lands and extra funds He raised a concern regarding the future of the project He expects that the project will help in the development of Narrabri Shire Influential Weakly in favour He can provide extra funds and lands for expansion Airport Authority of Australia Organization Sanction of the Project, Analysis of the need of the project The authority once raised an issue as to whether the project is actually necessary They expect that the project will help them gain more passengers Very Influential Strongly in favour The authority will help in the overall project and the operations Project Sponsor Sponsor Availability of sufficient funds Project sponsor raised a concern regarding the uncertain future of the project The project outcome will help the sponsor to gain significant benefits Influential Strongly in favour They will provide funds when needed Project Manager Manager Management of the whole project No issues raised The project will be completed successfully and in time Very Influential Strongly in favour Strong management and leadership skills Nearby Land Owners External Land disputes Land owners were not interested in letting go of their lands for airport expansion They will either get proper sum for the lands or proper relocation Limited Influence Strongly opposed Their demands should be met in order to stop land disputes Passengers Client More passengers will allow more airline companies to provide service Passengers are not sure whether the flights from the Narrabri Airport cost effective Passengers expect to reach all parts of Australia and other countries from Narrabri Airport in the future Influential Indifferent or undecided More passengers = more flights Local Public Services (Fire, Hospital, Security) External Provide emergency services The vastness of the project will require massive emergency services support They expect the project to be done abiding by all the safety guidelines Limited Influence Weakly opposed They will provide instant services in cases of emergency Employees Team Work as teams for the conduction of the project Rigorous working periods, insufficient allowances They expect personal benefits from their work in the project No Influence Indifferent or undecided The future of the project will depend on the works of the employees Project Management All these targets had to be met within a time span of around 2 years (Tonkin 2014). Hence, suitable management was necessary in order to meet all the targets successfully. In this project, step by step planning was undertaken. The following key events were planned and implemented (in numerical order): Closing of land disputes and acquiring all the necessary lands after analysis and measurements of the required area. Designing the blueprint of the plan. Operation of the expansion parts. Operation of the removal of unwanted structures. Building of infrastructures for new proposed structures. Other proposed building plans. The budget for the initial airport upgrade was $10.5 million and was funded by a $6m grant from NSW governments Resources for Regions contribution to Narrabri Shire Council, $3m from Whitehaven Coal and $1.5m in loan funds. After the steps were taken one after another, the project went on successfully and was finally finished within the specified timeline in 2015. With the step by step implementation, each of the parts of the project was completed successfully. Throughout the implementation phase, a risk analysis process was undertaken in order to identify possible risks and loopholes in the project (Tonkin 2014). This helped the authority to take necessary steps to remove any issues and other problems before it was too late. Moreover, suitable planning led the team to proceed with the next phase of the project successfully. The project manager was instrumental in whole of the project in this phase (2014-15). He analyzed all the tasks, delegated every task to the employees and workers and created a suitable timeline accordingly. He also added some extra time space periodically for risk analysis and other extra works. This enabled the employees to complete all the tasks effectively and successfully (Cast ro and Lohmann 2014). From this planning, the project manager had a number of benefits: Zero Extra Expenses As the timeline was produced according to plan, the project manager did not have to spend extra funds during the course of the project. Future Arrangements Due to successful implementation of the timeline, the project manager was able to analyze the success of the current phase and the requirements of the next phase. Sponsor Bonus Since the project was completed successfully in time, project manager earned some amount of sponsor bonus. The project was conducted successfully according to plan and no deviations from the main objectives were reported. Critical Analysis of Project Outcome From this project, as a manager, a lot of things has been learnt. Firstly, it was learnt that every project has to be carried out within a specified time. However, this needs efficient management and delegation of tasks. Implementation is another important factor. It was learnt that the implementations are to be done in a specific order in order to undertake a project successfully. Another important thing learnt was that risk assessment is always necessary in any project so that no problem is encountered in the future. As a manager, one should be able to show good leadership and management skills. One should be able to take suitable actions and decisions throughout the project. Again, from this project, it has been learnt that one should not proceed with any project that has no future. One should also not avoid his duties and delegate his tasks to someone else. The success of this project has helped to gain all the positives and the meaning of a true leader as a project manager. Conclusion In this report, an overall idea of the project and its details has been documented. The project targets, stakeholder analysis, implementations and benefits have been discussed. According to the Narrabri Airport Master Plan, several projects were set to be undertaken in a number of phases starting from 2014. In the first phase (2015-16), several targets were acquired and a timeline was set. The project manager and the whole management team sub-divided the tasks and revised the timeline for the implementation of each step one by one. Due to very efficient management, the initial phase of the project was completed within the specified timeline successfully. Reference List Adler, N., Fu, X., Oum, T.H. and Yu, C., 2014. Air transport liberalization and airport slot allocation: The case of the Northeast Asian transport market.Transportation Research Part A: Policy and Practice,62, pp.3-19. Bejarano, M.O., Duarte, J., Larson, D. and Roda, T., 2015, June. Case History: New South Runway Design and Construction at Fort Lauderdale International Airport: Geotechnical and Pavement Considerations. InAirfield and Highway Pavements 2015(pp. 375-385). Burghouwt, G., 2013. Airport capacity expansion strategies in the era of airline multi-hub networks. Castro, R. and Lohmann, G., 2014. Airport branding: Content analysis of vision statements.Research in Transportation Business Management,10, pp.4-14. Chevalier, J.M., 2016. Stakeholder analysis and natural resource management. Graham, A., 2015. The Key Airport Challenges. Kivits, R. and Charles, M.B., 2015. Aviation planning policy in Australia: Identifying frames of reference to support public decision making.Journal of Air Transport Management,47, pp.102-111. Projects, A. (2016). Projects View. [online] Aviation projects. Available at: https://www.aviationprojects.com.au/our-projects-view/narrabri-airport-upgrade-planning-5 [Accessed 5 Aug. 2016]. Ryerson, M.S. and Woodburn, A., 2016. Manage Flight Demand or Build Airport Capacity?.ACCESS Magazine,1(48). Sun, Y. and Schonfeld, P., 2015. Stochastic capacity expansion models for airport facilities.Transportation Research Part B: Methodological,80, pp.1-18. Tonkin, K. (2014). Narrabri Airport Master Plan 2014-2034. 1st ed. [ebook] Aviation Projects Pty Ltd, pp.9-15. Available at: https://www.narrabri.nsw.gov.au/files/uploaded/file/News%20Reel/YNBR02-01%20Narrabri%20Airport%20Master%20Plan%20v1_0%20140619%20with%20annexures%5B1%5D.pdf [Accessed 5 Aug. 2016]. Tu, C.S. and Chang, C.T., 2016. Using binary fuzzy goal programming and linear programming to resolve airport logistics center expansion plan problems.Applied Soft Computing,44, pp.222-237.

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.